Improved tension cable plates

Order #: 20260902180825-2977-11-0 · Created September 2, 2026
New Design Fabrication Delivery Complete
Project created Sep 2, 2026 · 6:08 PM
3 weeks ⚠ bottleneck risk
Deadline updated Sep 24, 2026 · 6:28 AM
Sep 22, 2026 → Oct 30, 2026 by Chris M. (Personal)
7 weeks ⚠ bottleneck risk
Deadline updated Nov 13, 2026 · 9:03 AM
Oct 30, 2026 → Dec 18, 2026 by Chris D. McCoy (You3Dit Inc.)
2 days
Design 1 submitted Nov 15, 2026 · 4:07 PM
by Buddy Magic
2 days
Quote 1 submitted Nov 17, 2026 · 5:22 PM
Buddy Magic — $16.00/unit via Bambu Lab X1-Carbon with AMS
17 hours
Design 2 submitted Nov 18, 2026 · 10:14 AM
by Buddy Magic
Project deadline Dec 18, 2026
NOW Design under review
Total elapsed: 11 weeks from project creation to last recorded event.