Order #20161207025159-672-01-0 · Created December 6, 2016
New
Design
Fabrication
Delivery
Complete
Project created
Dec 6, 2016 · 6:51 PM
3 days
Quote 1 submitted
Dec 9, 2016 · 10:51 AM
CDM (You3Dit Inc.) — $25.74/unit via Printrbot Simple Metal
2 weeks
⚠ bottleneck risk
Quote 2 submitted
Dec 24, 2016 · 6:01 PM
Sinan Toksoz — $25.00/unit via 3D MODEL RAISE 3D N2
108 weeks
⚠ bottleneck risk
Quote 3 submitted
Jan 19, 2019 · 8:29 PM
Derek — $35.00/unit via Prusa i3 MK3
NOW
Design approved — ready for quotes
Total elapsed:
111 weeks
from project creation to last recorded event.