Projects › Roped Calf Catcher › Timeline

Roped Calf Catcher

Order #: 20180408054052-1041-11-0 · Created April 7, 2018
New Design Fabrication Delivery Complete
Project created Apr 7, 2018 · 10:40 PM
6 weeks ⚠ bottleneck risk
Design 1 submitted May 22, 2018 · 4:36 PM
by Chip Douglas
2 days
Design 2 submitted May 24, 2018 · 10:28 AM
by Austin Campbell
19 weeks ⚠ bottleneck risk
Design 3 submitted Oct 2, 2018 · 7:29 AM
by Yingzhe Reginald Fu
425 weeks idle ⚠
STALLED Design under review 2974 days without activity
Total elapsed: 25 weeks from project creation to last recorded event.